🔨 Our contractors have advised that operatives will now be working on Saturdays between 8am – 1pm. There should be minimal noise and disruption, although lifting and moving machinery will be in use.
🛠️ Saturday working will continue as required and will be carried out in line with the planning approval for the site (hours: 8am – 1pm).
📅 Piling works are scheduled to resume – the second and final phase will start Monday, 22nd September.
🌱 Mesh screening has been installed to help reduce dust, and the wetter weather as the season changes should also help keep this to a minimum.
Before we move into the next phase, our Project Manager, Graham, would like to invite local residents to a site update meeting. This will be an opportunity to:
👷‍♂️ View the site plans and development progress
💬 Ask questions
🔎 Hear about the next steps – A newsletter with further details and updates will also be shared with local residents.
If you’d like to take part, please email us at Pensarn@cartreficonwy.org. We’ll confirm dates and arrangements shortly.
To apply for housing, contact the Homefinder team on 0300 124 0050

Last modified on September 12th, 2025 at 2:10 pm